Advanced Scheduling (Schedule Pro)

Pro tier only

The 7 commands in this group are Pro-only (flag SchedulePro). Standard-tier users see 🔒 lock icons and an "Upgrade to Pro" dialog when clicking.

Standard still includes basic Gantt + Auto Calc + Calendar Setup + AI suggestions + Schedule template — enough for simple projects.

7 Pro commands extending schedule-management capability for PMs / QS engineers / large-project schedulers:

CommandPurposeOutput
AI Schedule BuilderGenerate Gantt from Bill of Quantities (BoQ) using AISheet Gantt AI with task list + predecessors
EVM ReportEarned Value Management — PV/EV/AC/CV/SV/CPI/SPI + S-curveSheet EVM
Lookahead3-week look-ahead from Data DateSheet Lookahead 3W
BaselineCapture baseline schedule + compare with currentSheet Baseline
Variance DashboardPlanned vs Actual delta summary for every taskSheet Variance
Weekly SnapshotCapture weekly schedule statusSheet Snapshot YYYY-MM-DD
Trend SnapshotAggregate snapshots into a trend chartSheet Snapshot Trend
Schedule RecoveryAccelerate schedule (compress) + suggest optionsSheet Recovery

All commands live on ribbon DVD Cons → Schedule group.

AI Schedule Builder

DVD Cons → AI Schedule Builder.

Generates a Gantt outline from a Bill of Quantities ("Work item" + "Quantity" columns). Uses AI to:

  • Detect task dependencies (e.g. foundation → frame → roof → finishing)
  • Estimate duration based on TT10/2019 or ĐM1776 norm database
  • Auto-group summary tasks by level (1, 1.1, 1.1.1, ...)

Workflow

  1. Prepare BoQ sheet with columns: No. / Norm code / Task name / Unit / Quantity
  2. Select the BoQ range → click AI Schedule Builder
  3. Dialog asks: project Start date, crew, shifts/day
  4. AI generates Gantt AI sheet with task + predecessor + duration + resource

API key required

Requires a Gemini or ChatGPT API key in Preferences → AI tab. Gemini's free quota is sufficient for small-to-medium projects (~50 tasks).

EVM Report

DVD Cons → EVM Report.

Earned Value Management — analyzes actual project performance vs plan.

Required input

Gantt sheet must have:

  • Start / Finish columns (planned)
  • Actual Start / Actual Finish columns
  • % Complete column
  • Cost column or Budget at Completion (BAC)

Output

Sheet EVM contains:

ColumnFormulaMeaning
PV (Planned Value)BAC × % planned at Data DatePlanned earned value to date
EV (Earned Value)BAC × % actualActual earned value
AC (Actual Cost)Money spent so farCurrent cost
CVEV − ACCost variance (+ good, − bad)
SVEV − PVSchedule variance (+ good, − bad)
CPIEV ÷ ACCost performance (>1 good)
SPIEV ÷ PVSchedule performance (>1 good)
EACBAC ÷ CPIForecast total cost at completion

Includes S-curve chart (Planned / Earned / Actual over time).

3-Week Lookahead

DVD Cons → 3-Week Lookahead.

Generates Lookahead 3W sheet with all tasks whose Start or Finish falls within 21 days of Data Date. Grid layout:

CodeTask nameThis weekNext weekWeek after
MHC1130Pour foundation concrete▓▓▓▓▓░░░
MHC1140Build 1F walls▓▓▓▓▓▓

Used for weekly lookahead meetings with the site BCH (steering committee).

Baseline + Comparison

DVD Cons → Baseline.

Captures a snapshot of the schedule when the baseline is locked. Later, compare "current vs baseline" to track schedule slippage.

Workflow

  1. When the schedule is finalized and approved by BCH → click Baseline → "Save as Baseline #1"
  2. Hidden sheet BaselineData stores Start/Finish of every task at baseline time
  3. As construction progresses, the schedule changes → click Baseline → "Compare with Baseline #1"
  4. Dialog shows a report:
    • Slipped tasks (delta Start/Finish > 0)
    • Tasks completed early
    • Tasks added after baseline
    • Tasks deleted

Multiple baselines

Up to 3 baselines (e.g. Baseline 1 at start, Baseline 2 after Phase 1, Baseline 3 after revision 2). Compare between baselines to track trends.

Variance Dashboard

DVD Cons → Variance Dashboard.

Summary table of Planned vs Actual delta for every task. Layout:

CodeNamePlanned StartActual StartΔ StartPlanned FinishActual FinishΔ FinishStatus
MHC1130Foundation concrete01/0603/06+2d10/0612/06+2d🟡 late
MHC1140Wall building11/0611/06025/0623/06-2d🟢 early

Conditional formatting auto-colors:

  • 🟢 Early (Δ < 0)
  • ⚪ On schedule (Δ = 0)
  • 🟡 Slightly late (1-5d)
  • 🔴 Heavily late (>5d)

Weekly Snapshot + Trend

DVD Cons → Weekly Snapshot (capture) / Trend Snapshot (view trend).

Snapshot Capture

Click at the end of each week → generates Snapshot YYYY-MM-DD sheet recording:

  • Total project % complete
  • Number of tasks done / in progress / not started
  • Weekly CPI / SPI
  • Weekly critical path

Each snapshot is a separate sheet — never overwritten.

Snapshot Trend

Click to aggregate all snapshots into one trend sheet with charts:

  • Line chart: % complete by week
  • Line chart: SPI / CPI by week
  • Bar chart: tasks completed per week

Used for executive reporting — see if progress is on track.

Schedule Recovery

DVD Cons → Schedule Recovery.

When the schedule slips badly → dialog suggests acceleration options:

OptionDescriptionTrade-off
CrashAdd resources to critical tasks to shorten duration+Cost
Fast-trackRun sequential FS tasks in parallel as SS+Risk
Re-sequenceReorder non-critical tasksNeeds logic analysis
Scope cutDrop non-essential tasksNegotiate with owner

Dialog shows each option with:

  • Days saved
  • Cost increase / risk increase
  • Affected tasks

Generates Recovery sheet with the new plan + comparison to old plan.

License gating overview

CommandFree / ExpiredTrialStandardPro
Basic Gantt🔒
Calendar Setup🔒
Auto Calc
AI Schedule Builder🔒🔒
EVM Report🔒🔒
Lookahead🔒🔒
Baseline🔒🔒
Variance Dashboard🔒🔒
Snapshot capture/trend🔒🔒
Schedule Recovery🔒🔒

30-day Trial users get full Pro access but still see 🔒 icons (educational — so users know these are Pro features that lock after trial).