Manpower
Location on ribbon: Tab DVD Cons → Group Schedule → Menu Reports & Snapshot
Command ID: btnManpower
PRO feature
This command is part of the PRO plan. STANDARD accounts activated before 01/07/2026 keep access until their licence expires; other Standard accounts get an upgrade prompt when they click it.
What it does
Reads the manpower column on the schedule sheet (it recognises headings such as Nhân lực, Manpower or Crew), sums the workers active on each day, and plots a weekly peak histogram with an average reference line. Weeks above the average are highlighted as levelling candidates. This is the feasibility check most programmes skip: the logic looks fine, but one week demands 400 workers when the site can only accommodate 250.
How to use
- Open a schedule sheet whose manpower column is filled in per activity. Without such a column the command still runs and falls back to counting concurrent activities.
- Run Auto Calc so start and finish dates are current — the histogram spreads each crew over the activity's actual dates.
- Go to Tab DVD Cons → group Schedule → menu Reports & Snapshot → click Manpower.
- The command runs immediately: no dialog, no selection needed.
- Read the chart: each column is one week's peak headcount, the horizontal line is the average, and weeks above it are highlighted.
- Go back to the schedule, shift activities that still have positive float out of the peak weeks, then rerun to see whether the curve has flattened.
Example
Fit-out package on an office tower, planned average of 180 workers. The histogram reports:
| Week | Peak headcount | Against average |
|---|---|---|
| W31 | 165 | Below average |
| W32 | 172 | Below average |
| W33 | 268 | Over-allocated |
| W34 | 254 | Over-allocated |
| W35 | 141 | Below average |
Weeks 33–34 stack tiling, painting and ceiling crews on top of each other. The site manager pushes the ceiling crew back by one week (that activity still has 6 days of float) — the peak drops to 210, which fits the accommodation capacity without moving the completion date.
Notes
- The command is read-only: it never levels resources or moves dates for you — the decision to reschedule stays yours.
- The manpower heading must be one the command recognises (Nhân lực / Manpower / Crew); any other name sends it to the concurrent-activity fallback.
- Values are weekly peaks, not weekly averages, so the chart is a capacity and peak-load check.
- Blank manpower cells on some activities make the curve read lower than reality — fill them in before drawing conclusions.
- The chart sheet is regenerated on each run, and Ctrl+Z will not undo it.
Related
- Cash-flow — the same time-spreading logic applied to cost instead of labour.
- 3-Week Lookahead — inspect the weeks flagged as over-allocated in detail.
- Auto Calc — recompute dates and float before levelling anything.
- Gantt Chart — look at the bars to see which activities still have float to spend.