What it does

Audits your schedule network against the DCMA metric set (about 12 checks) — the same yardstick owners and supervision consultants use before approving a programme. The command scans the data already on the sheet and produces a Health sheet containing a scorecard plus the list of activities flagged by each check. Run it right before submitting a schedule, or after any major re-plan, to be sure the logic network has no open ends.

How to use

  1. Open the schedule sheet (a Gantt sheet with Code, Task name, Start, Finish and predecessor/successor columns).
  2. Run Auto Calc first so Total Float is populated — without it the negative-float and high-float checks cannot score correctly.
  3. Go to Tab DVD Cons → group Schedule → menu Reports & Snapshot → click Health Check.
  4. The command runs straight away: no dialog, no selection needed, and no extra columns to add — every metric is derived from existing data.
  5. Read the new Health sheet: each row is one metric with its value, target and result (Pass / Warn / Fail), and the overall health score sits at the bottom of the scorecard.
  6. Scroll down to the flagged-activity lists to see exactly which activity IDs to fix, correct them on the schedule sheet, then run the check again.

Example

You are about to submit a 320-activity master programme for an apartment tower package. After clicking the command, the Health sheet shows a scorecard like this:

MetricValueTargetResult
Open ends (missing pred./succ.)14 activities≤ 5%Fail
Leads (negative lag)3 relationships0Fail
FS relationship share81%≥ 90%Warn
Hard constraints (MSO)2 activities≤ 5%Pass
Negative float6 activities0Fail
Long durations (> 44 days)9 activities≤ 5%Warn

The planner links the 14 dangling activities, removes the 3 negative lags and reruns — the overall health score rises and the programme clears the consultant's review.

Notes

  • The command is read-only: it never changes dates or logic on the schedule sheet.
  • The Health sheet is overwritten on every rerun, and Ctrl+Z will not bring the previous one back.
  • Skip Auto Calc and Total Float stays empty, which makes the float and critical-path checks report wrong values.
  • BEI is only computed when the workbook already contains a saved Baseline; otherwise that row stays blank.
  • This checks network logic quality only — quantities, norms and manpower still need a manual review.
  • Auto Calc — run it first so the float metrics have Total Float to work with.
  • Baseline — save a baseline so the BEI metric has something to compare against.
  • Constraints — where you fix the hard constraints this check flags.
  • Variance Dashboard — the one-page management summary to produce once the schedule is clean.